Construction Update for the week of June 3, 2023.
Current Phase of Construction: Building Enclosure
What is Happening During the Next Week (June 3 – June 9, 2023)
- South façade installation is underway. This week, the crane on 124th Street will return to complete installing precast concrete panels on the upper floors.
- When panels are hoisted, pedestrian traffic will briefly be delayed until the panel is safely in the building structure.
- The work schedule of the crane will be 8:00 am – 6:00 pm, interior work and deliveries begin at 7:00 am.
- Interior work continues, which includes material deliveries; constructing the masonry walls on the east and west facades; electrical, plumbing and other MEP installation work.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
Construction Update for the week of May 27, 2023.
Current Phase of Construction: Building Enclosure
What is Happening During the Next Week (May 27 – June 2, 2023)
- South façade installation is underway. This week, the crane on 124th Street will leave the site temporarily. Interior work on the façade panels will be ongoing.
- Watch for further updates on the crane’s return to 124th Street.
- Interior work continues, which includes material deliveries; constructing masonry walls; electrical, plumbing and other MEP installation work.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
New Construction Update for the weekend of May 19-22, 2023.
- Weekend Street Closure: Twenty panels on the roof require a larger crane to install them safely. This crane will extend across 124th Street, so it will close the street to vehicular traffic from Adam Clayton Powell, Jr. Blvd. to Lenox Avenue and there will be no street parking available. To comply with DOT requirements, work will take place during the weekend, from 10:00 pm Friday, May 19 until 5:00 am Monday, May 22
- There will be no street parking available during those hours.
- Pedestrian access on 124th street sidewalk will be maintained; however, there will be intermittent sidewalk closures starting at 10:00 pm on Friday until 6:00 am on Monday morning.
Construction Update for the week of May 20, 2023.
Current Phase of Construction: Building Enclosure
What is Happening During the Next Week (May 20 – 26, 2023)
- South façade installation is underway. This week, the crane on 124th Street will continue installing precast concrete panels on the upper floors.
- When panels are hoisted, pedestrian traffic will briefly be delayed until the panel is safely in the building structure.
- The work schedule of the crane will be 8:00 am – 6:00 pm, interior work and deliveries begin at 7:00 am.
- Interior work continues, which includes material deliveries; constructing the masonry walls on the east and west facades; electrical, plumbing and other MEP installation work.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
New Construction Update for the weekend of May 13-14, 2023.
Weekend Street Closure Postponed:
- Due to a paperwork issue at DOB, work scheduled for this weekend will be delayed until next weekend, May 19-22.
- Permits for that weekend close 124th Street from Adam Clayton Powell, Jr. Blvd. to Lenox Avenue. from 10pm Friday evening until 5am Monday morning and there will be no street parking available during those hours.
- Pedestrian access on 124th street sidewalk will be maintained; however, there will be intermittent sidewalk closures starting at 10:00 pm on Friday until 6:00 am on Monday morning.
Construction Update for the week of May 13, 2023.
Current Phase of Construction: Building Enclosure
What is Happening During the Next Week (May 13 – 19, 2023)
- South façade installation is underway. This week, the crane on 124th Street will continue installing precast concrete panels on the upper floors.
- When panels are hoisted, pedestrian traffic will briefly be delayed until the panel is safely in the building structure.
- The work schedule of the crane will be 8:00 am – 6:00 pm, interior work and deliveries begin at 7:00 am.
- Interior work continues, which includes material deliveries; constructing the masonry walls on the east and west facades; electrical, plumbing and other MEP installation work.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday.
- Weekend Street Closure: Twenty panels on the roof require a larger crane to install them safely. This crane will extend across 124th Street, so it will close the street to vehicular traffic from Adam Clayton Powell, Jr. Blvd. to Lenox Avenue and there will be no street parking available. To comply with DOT requirements, work will take place during the weekend, May 12-15, from 10pm Friday evening until 5am Monday morning. Pedestrian access on 124th street sidewalk will be maintained; however, there will be intermittent sidewalk closures starting at 10:00 pm on Friday until 6:00 am on Monday morning.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
Construction Update for the week of May 6, 2023.
Current Phase of Construction: Building Enclosure
What is Happening During the Next Week (May 6 – May 12, 2023)
- South façade installation has begun. This week, the crane on 124th Street will continue installing precast concrete panels floors one and two.
- When panels are hoisted, pedestrian traffic will briefly be delayed until the panel is safely in the building structure.
- The work schedule of the crane will be 8:00 am – 6:00 pm, interior work and deliveries begin at 7:00 am.
- Interior work continues, which includes material deliveries; constructing the masonry walls on the east and west facades; electrical, plumbing and other MEP installation work.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday.
- After hours masonry work with some drilling will take place in the interior of the building. on Saturday, May 6. That work will begin after 9am.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
Weekend Street Closure: Twenty panels on the roof require a larger crane to install them safely. This crane will extend across 124th Street, so it will close the street to vehicular traffic from Adam Clayton Powell, Jr. Blvd. to Lenox Avenue and there will be no street parking available. To comply with DOT requirements, work will take place during the coming weekend, May 12-15, from 10:00 pm Friday evening until 5:00 am Monday morning.
Construction Update for the week of April 29, 2023.
Current Phase of Construction: Building Enclosure
What is Happening During the Next Week (April 29 – May 6, 2023)
- South façade installation has begun. This week, the crane on 124th Street will be installing precast concrete panels on the roof and then the ground floor.
- When panels are hoisted, pedestrian traffic will briefly be delayed until the panel is safely in the building structure.
- The work schedule of the crane will be 8:00 am – 6:00 pm, interior work and deliveries begin at 7:00 am.
- Interior work continues, which includes material deliveries; constructing the masonry walls on the east and west facades; electrical, plumbing and other MEP installation work.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday
- After hours masonry work with some drilling will take place in the interior of the building on Saturday, April 29. That work will begin after 9am.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
Construction Update for the week of April 22, 2023.
Current Phase of Construction: Building Enclosure
What is Happening During the Next Week (April 22 – April 29, 2023)
- Interior work continues, which includes material deliveries, constructing the masonry walls on the east and west facades, electrical, plumbing, and other MEP installation work
- Preparation of the site for the arrival of the crane on 124th Street later next week
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday
- South façade panel installation is planned to begin next week. When panels are hoisted, pedestrian traffic will briefly be delayed until the panel is safely in the building structure. The work schedule of the crane will be 8:00 am – 6:00 pm, interior work and deliveries begin at 7:00 am
- After hours masonry and drywall work will take place in the interior of the building on Saturday, April 22
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
Construction Update for the week of April 15, 2023.
Current Phase of Construction: Building Enclosure
What is Happening During the Next Week (April 15 – April 22, 2023)
- Interior work continues, which includes material deliveries; constructing the masonry walls on the east and west facades; electrical, plumbing and other MEP installation work.
- Preparation of the site for the arrival of the crane on 124th Street later this month.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday
- South façade panel installation is planned to begin later this month. When panels are hoisted, pedestrian traffic will briefly be delayed until the panel is safely in the building structure. The work schedule of the crane will be 8:00 am – 5:30 pm, interior work and deliveries begin at 7:00 am.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
The Studio Museum in Harlem Construction Update for the week of April 8, 2023.
Current Phase of Construction: Building Enclosure
What is Happening During the Next Week
- Interior work continues, which includes material deliveries; constructing the masonry walls on the east and west facades; electrical, plumbing and other MEP installation work.
- Preparation of the site for the arrival of the crane on 124th Street later this month.
- Regular work hours 7:00 a.m. to 5:30 p.m., Monday through Friday
- South façade panel installation is planned to begin later this month. When panels are hoisted, pedestrian traffic will briefly be delayed until the panel is safely in the building structure. The work schedule of the crane will be 8:00 a.m.-5:30 p.m., interior work and deliveries begin at 7:00 a.m.
Please note that all activities are subject to change based on weather and other field conditions-
What To Expect
- Regular working hours are 7:00 a.m. to 5:30 p.m. Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
Construction Update for the week of April 1, 2023.
Current Phase of Construction: Building Enclosure
What is Happening During the Next Two Weeks (April 1 – April 15, 2023)
- Interior work continues, which includes material deliveries; constructing interior masonry walls; electrical, plumbing and other MEP installation work.
- Preparation of the site for the arrival of the crane on 124th Street.
- Regular work hours 7:00 a.m. to 5:30 p.m., Monday through Friday
- South façade panel installation will begin on 124th Street during the week of April 10. The work schedule of the crane will be 8:00 a.m.-5:30 p.m., interior work and deliveries begin at 7:00 a.m. When panels are hoisted, pedestrian traffic will briefly be delayed until the panel is safely in the building structure. There may be occasional temporary street closures during work hours.
Please note that all activities are subject to change based on weather and other field conditions-
What To Expect:
- Regular working hours are 7:00 a.m. to 5:30 p.m. Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
Construction Update for the week of March 23, 2023.
Current Phase of Construction: Building Enclosure
What is Happening During the Next Week (March 23–March 31, 2023) – 125th Street
- North Façade Panel Installation has completed and the crane has left 125th Street.
What is Happening During the Next Week (March 18–March 25, 2023) – 124th Street:
- Interior work continues, which includes material deliveries; constructing the masonry walls on the east and west facades; electrical, plumbing and other MEP installation work.
- Preparation of the site for the arrival of the crane.
- Regular work hours 7:00 a.m. to 5:30 p.m., Monday through Friday
- After hours masonry and drywall work will take place in the interior of the building on Saturday, April 1 from 9:00 a.m.-5:00 p.m.
- South façade panel installation will begin the week of April 3. When panels are hoisted, pedestrian traffic will briefly be delayed until the panel is safely in the building structure. The work schedule of the crane will be 8:00 a.m.-5:30 p.m., interior work and deliveries begin at 7:00 a.m.
Please note that all activities are subject to change based on weather and other field conditions-
What To Expect:
- Regular working hours are 7:00 a.m. to 5:30 p.m. Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
Construction Update for the week of March 18th, 2023.
Current Phase of Construction: Building Enclosure
What is Happening During the Next Week (March 18–March 25, 2023) – 125th Street
- North Façade Panel Installation with crane. When panels are hoisted, pedestrian traffic will briefly be delayed until the panel is safely in the building structure.
- Moderate noise may occur during this phase of construction.
- The 125th Street façade panel installation phase is anticipated to complete in Spring 2023.
- This work is scheduled at night to mitigate the impact on pedestrian traffic, neighboring businesses, and bus traffic. Work schedule is 9:30 pm-5:30 am.
What is Happening During the Next Week (March 18–March 25, 2023) – 124th Street:
- Interior work continues, which includes material deliveries; constructing the masonry walls on the east and west facades; electrical, plumbing and other MEP installation work.
- Regular work hours 7:00 am-5:30 pm, Monday through Friday
- After hours masonry and drywall work will take place in the interior of the building on Saturday, March 18 from 9:00 am-5:00 pm.
Please note that all activities are subject to change based on weather and other field conditions-
What To Expect:
- Regular working hours are 7:00 am to 5:30 pm Monday to Friday. After hours work on 125th Street only will take place from 9:30 pm to 5:30 am. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
Construction Update for the week of March 11th, 2023.
Current Phase of Construction: Building Enclosure
What is Happening During the Next Week (March 11–March 18, 2023) – 125th Street
- North Façade Panel Installation with crane. When panels are hoisted, pedestrian traffic will briefly be delayed until the panel is safely in the building structure.
- Moderate noise may occur during this phase of construction.
- The 125th Street façade panel installation phase is anticipated to complete in Spring 2023.
- This work is scheduled at night to mitigate the impact on pedestrian traffic, neighboring businesses, and bus traffic. Work schedule is 9:30pm-5:30am.
What is Happening During the Next Week (March 11–March 18, 2023) – 124th Street:
- Interior work continues, which includes material deliveries; constructing the masonry walls on the east and west facades; electrical, plumbing and other MEP installation work.
- Regular work hours 7am-5:30 pm, Monday through Friday
- After hours masonry and drywall work will take place in the interior of the building on Saturday, March 11 from 9am-5:00pm.
Please note that all activities are subject to change based on weather and other field conditions-
What To Expect:
- Regular working hours are 7:00 a.m. to 5:30 p.m. Monday to Friday. After hours work on 125th Street only will take place from 9:30pm to 5:30am. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
Construction Update For the week of March 6th, 2023.
Current Phase of Construction: Building Enclosure
- What is Happening During the Next Week (March 6 – March 10) – 125th Street:
- North Façade Panel Installation with crane. When panels are hoisted, pedestrian traffic will briefly be delayed until the panel is safely in the building structure.
- Moderate noise may occur during this phase of construction.
- The 125th Street façade panel installation phase is anticipated to complete in Spring 2023.
- This work is scheduled at night to mitigate the impact on pedestrian traffic, neighboring businesses, and bus traffic. Work schedule is 9:30pm-5:30am.
- What is Happening During the Next Week (March 6 – March 10) – 124th Street:
- Interior work continues, which includes material deliveries; constructing the masonry walls on the east and west facades; electrical, plumbing and other MEP installation work.
- Regular work hours 7am-5:30 pm, Monday through Friday
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 a.m. to 5:30 p.m. Monday to Friday. After hours work on 125th Street only will take place from 9:30pm to 5:30am. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
Construction Update February 27, 2023
Current Phase of Construction: Building Enclosure
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am to 4:00 pm Monday to Friday. After-hours work on 125th Street only will take place from 10:30 pm to 5:30 am. Note that contractors may mobilize on site approximately thirty to forty-five minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.