Building Updates and Construction Notifications
Please check the website for biweekly construction updates.
October 1–31, 2024.
Current Phase of Construction: Interior Construction
What is Happening During October:
- Interior work continues, which includes material deliveries; interior finishes; electrical, wiring and systems commissioning work.
- Exterior work on the roof continues for installation of pavers and planters.
- In the coming weeks, the sidewalk shed on 124th Street and 125th Street will be removed and pedestrian access will be restored to the sidewalks. When DOB approval is obtained we will provide an update here.
- Regular work hours 7:00 am – 6:00 pm, Monday through Friday.
- No after hours work is scheduled.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
September 16 and 23, 2024
Current Phase of Construction: Interior Construction
What is Happening During the Next Two Weeks:
- Interior work continues, which includes material deliveries; interior finishes; electrical, wiring and systems commissioning work.
- Exterior work on the roof continues for installation of pavers and planters.
- In the coming weeks, the sidewalk shed on 124th Street and 125th Street will be removed and pedestrian access will be restored to the sidewalks.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday.
- No after hours work is scheduled.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
August 12 and 19, 2024
Current Phase of Construction: Interior Construction
What is Happening During the Next Two Weeks
- Interior work continues, which includes material deliveries; interior finishes; electrical, wiring and MEP commissioning work.
- Exterior work on the roof continues for installation of pavers and planters.
- Façade caulking and cleaning will take place on 124th Street and 125th Street. This work will continue for approximately 2 weeks. Until this work is completed, the sidewalk sheds on both 124th and 125th Street are required to be in place.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday.
- No after hours work is scheduled.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
June 17 and June 24, 2024
Current Phase of Construction: Interior Construction
What is Happening During the Next Two Weeks
- Interior work continues, which includes material deliveries; interior finishes; electrical, wiring and MEP commissioning work.
- Exterior work on the roof continues for installation of pavers.
- Façade caulking and cleaning will take place on 124th Street and 125th Street. This work will continue for approximately 2 weeks.
- Until this work is completed, the sidewalk sheds on both 124th and 125th Street are required to be in place.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday.
- No after hours work is scheduled.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
June 7 and June 14, 2024
Current Phase of Construction: Interior Construction
What is Happening During the Next Two Weeks
- Interior work continues, which includes material deliveries; interior finishes; electrical, wiring and MEP commissioning work.
- Exterior work on the roof continues for installation of pavers.
- Façade caulking and cleaning will take place on 124th Street and 125th Street. This work will continue for approximately 3-4 weeks. Until this work is completed, the sidewalk sheds on both 124th and 125th Street are required to be in place.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday.
- After hours work is scheduled for Saturday, June 8; Sunday, June 9; and Saturday, June 15. The work will include interior work, and exterior roof work, weather permitting.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
May 27 and June 3, 2024
Current Phase of Construction: Interior Construction
What is Happening During the Next Two Weeks
- Interior work continues, which includes material deliveries; interior finishes; electrical, wiring and MEP commissioning work.
- A concrete pour for sidewalk on 124th Street is scheduled for Wednesday, May 29.
- Exterior work on the west facade and the roof continues for waterproofing installation. Installation of railings will begin on the roof terrace, 5th floor balcony and art niches on both the north and south facades. This work will continue for approximately 3-4 weeks. Until this work is completed, the sidewalk sheds on both 124th and 125th Street are required to be in place.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday.
- After hours work is scheduled for Saturday, June 1 and 8. The work will include interior work, and exterior railing work, weather permitting.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
May 13 and 20, 2024
Current Phase of Construction: Interior Construction
What is Happening During the Next Two Weeks
- Interior work continues, which includes material deliveries; interior finishes; elevator, electrical, wiring and other MEP installation work.
- Exterior work on the east and west facades as well as the roof continues for waterproofing installation. Railings are being installed on the roof terrace and art niches.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday.
- After hours work is scheduled for Saturday, May 18 and 25. The work will include interior work, and exterior roof work, weather permitting.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
May 3 and 10, 2024
Current Phase of Construction: Interior Construction
What is Happening During the Next Two Weeks
- Interior work continues, which includes material deliveries; interior door and partition installation; elevator, electrical, plumbing, wiring and other MEP installation work.
- Exterior work on the east and west facades as well as the roof continues for waterproofing installation.
- Concrete for the sidewalk on 125th Street will be poured. A small concrete truck will be adjacent to the site.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday. After hours work is scheduled for Saturday, May 4 and 11. The work will include interior work, and exterior roof work, weather permitting.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
April 15 and 22, 2024
Current Phase of Construction: Building Enclosure and Interior Construction
What is Happening During the Next Two Weeks
- Interior work continues, which includes material deliveries; interior door and partition installation; elevator, electrical, plumbing, wiring and other MEP installation work.
- Exterior work on the east and west facades as well as the roof continues for waterproofing installation and skylight installation.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday.
- After hours work is scheduled for Saturday, April 20 and 27. The work will include interior work, and exterior roof work, weather permitting.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
April 8, 2024
Current Phase of Construction: Building Enclosure and Interior Construction
What is Happening This Week:
- The protected pedestrian walkway on 125th Street has been moved to the parking lane of the street due to reconfiguration of the sidewalk shed.
- Interior work continues, which includes material deliveries; interior door and partition installation; elevator, electrical, wiring and other MEP installation work, tiling and painting.
- Exterior work on the east and west facades as well as the roof continues for installation of waterproofing and skylight installation.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday.
- After hours work is scheduled for Saturday, April 13. The work will include interior work, and some exterior work on the facades if weather permits.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
April 1 and 8, 2024
Current Phase of Construction: Building Enclosure and Interior Construction
What is Happening During the Next Two Weeks
- Interior work continues, which includes material deliveries; interior door and partition installation; elevator, electrical, plumbing, wiring and other MEP installation work.
- Exterior work on the east and west facades as well as the roof continues for waterproofing installation and skylight installation.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday
- After hours work is scheduled for Saturday, April 6 and April 13. The work on April 6 will include exterior work: sidewalk shed reconfiguration on 125th Street; a concrete pour at the loading dock which will involve concrete trucks on 124th Street; and exterior wall work on east and west facades.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.
March 18 and 25, 2024
Current Phase of Construction: Building Enclosure and Interior Construction
What is Happening During the Next Two Weeks
- Interior work continues, which includes material deliveries; interior door and partition installation; elevator, electrical, plumbing, wiring and other MEP installation work.
- Exterior work on the east and west facades as well as the roof continues for waterproofing installation and skylight installation.
- Regular work hours 7:00 am – 5:30 pm, Monday through Friday.
- After hours work is scheduled for Saturday, March 23 and March 30. The work will include interior work.
Please note that all activities are subject to change based on weather and other field conditions.
What To Expect:
- Regular working hours are 7:00 am – 5:30 pm Monday to Friday. Note that contractors may mobilize on site approximately 30 to 45 minutes before work commences.
- Although contractors carefully stage construction activities to minimize disruption to the surrounding community, the nature of construction work is such that some disruptions will occur. Expect some noise, vibration, dust, and other related impacts due to construction. The project adheres to a comprehensive clean construction program and mitigation protocols, including dust control and noise mitigation. Noise mitigation requirements are posted on the site construction fence and are monitored regularly by the Department of Environmental Protection.